Department of Public Works

-A A +A

Hours of Operation

Monday - Friday 8:00 am - 4:00 pm

Emergency (Nights, Weekends, Holidays), contact Bedford Police Department at 781-275-1212

Phone

(781) 275-7605

Fax

781-275-9010

After Hours Phone Number

781-275-1212

Emergency Numbers

781-275-1212

Address

314 The Great Road
Bedford, MA 01730
United States
Major Happenings

Notice
What’s Happening in Flint Michigan and How is MWRA’s Water Quality Different

1/29/2016

Water System and MWRA

Safe Routes to School Program
2/18/2016 Updated

John Glenn Middle School
Great Road, Mudge Way, Railroad Avenue

            Recently the Massachusetts Department of Transportation, MassDOT, notified the Town of Bedford that we have been approved for funding under their Safe Routes to School Program for improvements to pedestrian and bicycle access to the John Glenn Middle School from Great Road via the Bedford High School lot.  The project includes a new traffic control signal at Mudge Way and designated bike lanes along Mudge Way from Great Road to the Jenks Trail. The Jenks Trail will be widened about two feet to accommodate bicyclists and pedestrians.  At the southerly end of the Jenks Trail, pedestrians and bicyclists will cross the driveway with a new marked crosswalk and continue to the Middle School over an improved pathway.  There will also be a formal crossing between the Tot Lot and the sidewalk to the Bedford Library.     

This project has been programmed for bidding later in 2016.  The engineering firm of TEC has been expediting the design to ensure that the project stays on schedule.  The spring Town Meeting will include an article to designate Mudge Way as a public way and to set permanent easements over the proposed improvements.  MassDOT conducted a public meeting on February 11th at the John Glenn Middle School to present the plans and answer questions from residents and stake holders.  Please click here to see the concept plans and presentation slides. 

Fawn Lake Preservation Study
December 2015

1/21/2016 UPDATED

The Fawn Lake Preservation Study was recently prepared to identify the current conditions of the pond including sediment thickness and composition, chemical analysis and water depth.  The aquatic vegetation has regrown in spite of previous efforts to hydrorake and follow-up with herbicide treatment.   If no significant action is performed, the plants will eventually overtake the open water, revert the pond to a wet marsh and eliminate recreational activities such as canoeing and fishing at the site.   

The newly formed Fawn Lake Committee has been working to evaluate all of the options outlined in the Study, as presented by its consultant, CEI.  The Committee weighed each option with respect to longevity, cost, permitting and environmental/neighborhood impacts.   The Committee has concluded that hydraulic wet dredging is the most suitable technique for a long term, viable solution that will also restore the recreational activities of fishing, canoeing and ice skating.  Removing the sediments and increasing the water depth will also inhibit future plant growth.

The Committee has requested $100,000 from Community Preservation to fund the design, specifications and environmental permitting for the dredging operation.  The work will also include a strategy to replace the Fawn Lake Dam which has been rated in poor condition.  Please click here for additional information presented to the various Town boards and committees
 

Fawn Lake - January 2016
2/24/2016 UPDATED
Please click here for additional information.
 

2015
Pedestrian / Bicycle Master Plan

 

Presentation to Selectmen - September 8th

2015 Bedford Bicycle Pedestiran Plan 1/4/2016

Middlesex Turnpike Phase 3
12/29/2015

 Phase 3 of the Middlesex Turnpike Roadway Improvement Project is scheduled to begin in 2017.  It is the last of a multi-phase, multi-year program to improve traffic through the Tri-Town corridor linking Burlington, Bedford and Billerica.  The limits of this project are from Crosby Drive/Plank Street in Bedford to Manning Road in Billerica.  Similar to the other phases of the project, Middlesex Turnpike will be widened to two lanes in each direction with protected left turn lanes at all driveways.  In addition, new traffic control signals will be installed at Oak Park Drive in Bedford and 900 Middlesex Turnpike and Manning Road in Billerica.  There will be bike lanes and sidewalks along both sides of the roadway.  Utility poles will be relocated to accommodate the widened cross section and new LED’s street lights will be installed.  Significant work will take place to widen the roadway at the Shawsheen River.  The project is funded by the Massachusetts Department of Transportation and is expected to take 3 years to complete.

Bedford-Abutter-Meeting-12-16-15

 

General Information

 

2016 Enviormental Scholarship Award

Bedford High School seniors Trenton Sanders (center) and Avery Kaplan were named recipients of the 2016 Environmental Scholarship. Bedford Recycling Coordinator Ed McGrath (left), Republic Services General Manager Chris Peters and Michael Griffin, Program Administrator for Science at Bedford High, (right) presented the award at BHS in May. Each student will receive a $1,400 scholarship.


 

 

April 2016 Pavement Managment Study
5/15/2016

Report

 

Notice
Bedford's Source Water Assessment Report

3/16/2016

SWAP Report

 

Notice
Drinking Water test results 2016 MWRA

7/07/2016 Updated

MWRA Water Quality report

 

Notice
Winter Snow removal Operations

1/6/2016

The Town of Bedford Public Works Department is pleased to issue the following guide to winter snow removal operations.  This information is meant to inform Bedford residents of the snow plowing and sidewalk clearing procedures and to ask for your assistance so that the town roads can be restored for safe travel as quickly as possible following a winter storm.  Snow plowing is a time consuming and laborious job.  Your cooperation is essential and we thank you for your patience.

Please click herefor additional information

 

Notice
Narrow Gauge Trail Stone Dust Path Refurbishment

The Bedford Selectmen recently awarded a contract to Sunshine Paving to refurbish the stone dust path along the Narrow Gauge Rail Trail between Great Road and the Billerica town line.  The work includes removal of the existing material to reestablish a 10 foot wide compacted stone dust path.  The two parking areas will also be reworked to provide a uniform grade and resurfaced with new stone dust.  The project is expected to begin on December 1st and be completed in approximately two weeks, weather dependent.  The Town will have a uniformed police detail at the work site to assist users to cross the construction area, but please use caution along the path.  For additional information, please contact the Department of Public Works at (781)  275-7605.

Narrow Gauge Plan

 

Notice
Drinking Water Update

1/02/2015

Primary source is from Massachusetts Water Resource Authority – MWRA : 85% - 90% supply
Secondary source is from the Shawsheen Road Wellfield: 10% - 15% supply
On average 1.2 million gallons of water is used each day

Drinking Water Update
 

 

Fawn Lake Preservation Study
04/ 17 / 2015 updated

The Bedford Selectmen recently appointed nine residents to serve on the newly formed Fawn Lake Committee.  These members represent the Selectmen, Conservation Commission, Historical Preservation Committee, Land Stewards, the Fawn Lake community action group and other interested citizens.  Town staff from Conservation and DPW will attend the meetings and provide technical assistance and committee coordination. 

The Fawn Lake Preservation Study, funded by the Community Preservation Committee and prepared by CEI Consultants, Inc., has resulted in a baseline inventory and analysis of current conditions at Fawn Lake.  Two public meetings were held in late 2015 for CEI to explain their field work results and gather public input.  A final report was recently submitted to the Town, which outlines 15 possible strategies, including benefits, permitting requirements and estimated costs.  Using the Study, the Fawn Lake Committee will review and evaluate the options for preserving Fawn Lake as an open water body.  Their selection and recommendation of an option or combination of options will be presented to the Commission and Selectmen at an advertised public meeting. 

Fawn Lake Public Meeting October 29, 2014

Fawn Lake Public Meeting December 3, 2014

Latin Names of Identified Plant Species in Fawn Lake, October 2014

Fawn Lake Presveration Study, March 2015 ( New )

------------------------------------------------------------------------------

 

Minuteman Bikeway Extension Project
0321/2016 updated

The Town of Bedford recently received approval from the Massachusetts Department of Transportation to fund the extension of the Minuteman Bikeway.  The Bikeway currently ends at Depot Park, near the intersection of South Road and Loomis Street.  This project proposes to extend the bikeway by making a portion of Railroad Avenue accessible to bikes, and constructing 8,800 feet of bikeway on the Reformatory Branch Trail, from Railroad Avenue to the Bedford/Concord Town line.  The new bikeway will have a 12 foot wide paved section with 3 foot wide clear zones on both sides.

The existing Minuteman Bikeway is used as a transportation corridor for regional commuters as well as local residents.  Extending the bikeway westerly to the town line will provide on-road connections to Railroad Avenue, Hartwell Road and Concord Road in addition to providing access to the schools and several Town owned parcels and conservation areas.  

The paved width of Railroad Avenue varies between 20 and 27 feet.  The pavement is in poor condition, and although it’s in close proximity to the John Glenn Middle School and Bedford High School, it only provides intermittent sidewalks.  As part of the project, the trail crossing at the tight curve on Railroad Avenue will be enhanced with activated flashing beacons, and the two existing parking areas will be reconstructed.

Please click here for the public presentation on June 9, 2014.
Please click here for the public presentation on August 4, 2014
Please click
here for the public presentation on Nov. 3, 2014
Please click here for the public presentation on April. 27, 2015
Please click here for the public presentation on May. 13, 2015
Please click
here for the public presentation on March.14,2016
 

 

Notice
Street opening Moratorium

12/29/2015 - Updated

The Department of Public Works has a 5-year moratorium for trenching or cutting a newly paved roadway to preserve the investment of the Town’s reconstruction funds. This applies to applications for new gas, electric, cable, fiber or telephone service. Please refer to the following list of streets when planning or designing a new house or other development.

Street Opening Moratorium Pdf
Updated

 

Notice
Minutman Bikeway Recomendations
Report by Toole Design Group for the

Towns of Bedford, Lexington and Arlington
 

Navigating the Minuteman Commuter Bikeway
 

 

Current Projects

 

Notice
Water Main Improvement Project

07/18/2016 NEW

Ashby Road                                              Bacon Road

Walsh Road                                              Crescent Avenue

Lane Avenue                                             Hartford Street

Winthrop Avenue

Plans: C&L 2016 - Walsh and Ashby - Bid Plans P01
            C&L 2016 - Walsh and Ashby - Bid Plans P02
            C&L 2016 - Walsh and Ashby - Bid Plans P03

 

          The Bedford Selectmen recently awarded a contract to Biszko Contracting to clean and line the water mains in the above noted areas.  The cleaning and lining process scrapes off deposits within the water main and then applies a cement liner to the inside of the pipe to prohibit the future growth of rust.     

In order to perform this work, the existing water main will be taken out of service.  Temporary pipes will be set above ground and houses will be connected to the temporary pipe from hoses connected to an outside sillcock.     

Hydrant connections will be in place to maintain fire protection.

The project will start the week of July 18th on Ashby Road, Walsh Road, Lane Avenue and Winthrop Avenue.  Work hours will be Monday thru Thursday, 7:00 am to 5:00 pm, weather dependent.  The roads will remain open, although minor delays around the construction site should be expected.   Once the above streets are complete, Biszko will begin work on Bacon Road, Crescent Avenue and Hartford Street. The project should be complete by the end of October.

            Bedford Water Division personnel will be overseeing this project.  Should you have any questions or need additional information, please contact the DPW at (781) 275-7605.   

 

Staff Contacts

Name Title Phone
Jack Landers
Syndicate content